SIDT : 1B
Activity No : 1.1.2
District: Matale
-
Udatenna Tank Silt-Trap Construction

Status: 80% Completed
Implementing Agency: Provincial Irrigation Department – Matale
DS Division: Naula
GN Division: Halambagawatta
Geographical Coordinates: 7.444374 N, 80.425119 E
Paddy Area Served: 55 Acres
Beneficiary Families: 28
Associated Initiative: Support to Moragahakanda Reservoir Desilting
Progress Summary:
Construction of the silt-trap at Udatenna tank is progressing well, with 80% of physical work completed by the reporting period. Earthwork and excavation activities have been finalized, while finishing and slope stabilization are ongoing. The intervention aims to reduce silt inflow into downstream irrigation channels and the Moragahakanda reservoir, enhancing long-term water storage efficiency.
Field Observation:
The structure is nearing completion with proper compaction and channel alignment observed during inspection. Local farmers have expressed positive feedback on expected improvements in paddy land irrigation reliability.